• Home
  • Beginners
  • Knowledge Areas
    • Integration
    • Scope
    • Schedule
    • Cost
    • Quality
    • Resource
    • Communications
    • Risk
    • Procurement
    • Stakeholder
  • Process Flow
  • Reference Materials
    • Books
    • Exam Prep Courses
    • Practice Questions
  • Tips
  • Lessons Learned
  • About

PM DRILL

PMP exam guide

You are here: Home / Study Tips / The Best Collection of PMP Formulae

The Best Collection of PMP Formulae

November 23, 2017 By Manickavel Arumugam 4 Comments

7
SHARES
ShareTweet

The Best Collection of PMP Formulae

Interested to grab some easy marks in the PMP exam?

Don’t lose sleep over PMP formulae.

The numerical questions in PMP exam are relatively easier.

Score easy marks by understanding few PMP formulae; and practice simple problems that applies these PMP formulae to project scenarios.

In this article, I have covered the most commonly used PMP formulae. Use this as a handy reference to help you learn, memorize the PMP formulae and practice thousands of PMP questions. Please note that numerical problems are extremely easy to score marks in the exam. So, your effort on learning the PMP formulae will be worth it.

Table of Contents

  • Project Selection Methods
  • Critical Path Method
  • PERT Analysis with Beta Distribution
  • Project Cost Management
  • Earned Value Management
    • Estimate At Completion (EAC)
    • To-Complete Performance Index (TCPI)
  • Project Risk Management
  • Project Communications Management
  • Conclusion

Project Selection Methods

Future  Value FV = PV (1+i)n
Present  Value PV = FV / (1+i)n
Benefit Cost Ratio = Benefit/ Cost

where
i = rate of interest
n = duration

Critical Path Method

Total Float of an activity = LS – ES (or) LF-EF
Free Float of an activity = (ES)Successor – EF

where
ES = Early Start
EF = Early Finish
LS = Late Start
LF = Late Finish

PERT Analysis with Beta Distribution

Expected duration of an activity te = (O+4M+P) / 6
Standard deviation of an activity σ = (P – O) / 6
Variance of an activity = σ2

where
O = Optimistic duration
M = Most likely duration
P = Pessimistic duration

One Standard Deviation (1σ) = 68.26% chance that an activity will be completed in the range (te ±1σ) duration
2σ = 95.46% chance
3σ = 99.73% chance
6σ = 99.99% chance

Project Cost Management

Cost Baseline = Estimated Project Cost + Contingency Reserve
Project Budget = Cost Baseline + Management Reserve

Earned Value Management

Schedule Variance SV = EV – PV
Schedule Performance Index SPI = EV / PV
Cost Variance CV = EV – AC
Cost Performance Index CPI = EV / AC
Estimate To Complete ETC = EAC – AC
Variance At Completion VAC = BAC – EAC

where
EV = Earned Value
PV = Planned Value
AC= Actual Cost
BAC = Budget At Completion

Tip: Remember that all the right hand side of the first four formulae above starts with EV.

Estimate At Completion (EAC)

EAC = AC + (BAC – EV)
[use this formula if current project performance is atypical; you expect the project to perform to original expectation from now on]
EAC = AC + (BAC – EV) / CPI = BAC / CPI
[use this formula if current project performance is typical; you expect the project to perform similarly till end of the project]
EAC = AC + (BAC – EV) / (SPI x CPI)
[use this formula if you want to complete the project in time, irrespective of what has happened so far]

To-Complete Performance Index (TCPI)

TCPI = (BAC – EV) / (BAC – AC)
[based on BAC]
TCPI = (BAC – EV) / (EAC – AC)
[based on EAC]

Project Risk Management

Expected Monetary Value EMV = Probability x Impact

Project Communications Management

Number of communication channels = n (n-1) / 2

Where n = number of stakeholders involved

Conclusion

I tried to provide you with the best collection of PMP formulae. Please understand each formula. If you have any queries on the above PMP formulae, please leave a comment below. Let us discuss and understand the formulae better.

Did I miss any important PMP formula? Please do me a favour by bringing it to my attention. I will update the article so that other PMP aspirants also get the benefit.

  • Author
  • Recent Posts
Manickavel Arumugam
Follow Me
Manickavel Arumugam
Certified Project Management Professional (PMP)®
Certified Risk Management Professional (PMI-RMP)®
An enthusiastic project management practitioner and trainer.
Manickavel Arumugam
Follow Me
Latest posts by Manickavel Arumugam (see all)
  • Yet another PMP Success Story - October 21, 2019
  • Project Management Using Microsoft Excel - September 10, 2019
  • PMI-RMP Course by uCertify – Is it for You? - August 3, 2019
7
SHARES
ShareTweet

Filed Under: Study Tips

Most Shared Posts

Comments

  1. DMurali says

    May 24, 2020 at 1:42 pm

    Hi Sir,

    Thank you for explaining it. So the 3 formulas to calculate EAC are,

    1) EAC = BAC/CPI –> use when project is expected to perform the same for the remainder of the project
    2) EAC = AC+(BAC-EV) –> use when you expect the project to perform as planned from now on.
    3) EAC = AC = [(BAC-EV)/(CPI*SPI)] –> use when you want the project to complete on time regardless of what has happened so far.

    Is this correct?

    Reply
    • Manickavel Arumugam says

      May 25, 2020 at 8:16 am

      Yes, correct.

      Small correction in the third formula. It should read as:
      EAC = AC+(BAC-EV)/(CPI*SPI)

      The third formula is used when both CPI and SPI are taken into account. Here, it is also assumed that the project will perform similarly for the remainder of the project; in addition, you also want to stick to the original schedule. Two conditions in this formula, from schedule perspective and cost perspective.

      Reply
  2. DMurali says

    May 23, 2020 at 4:14 pm

    I noticed that the below EAC calculation is incorrect. There are 4 ways to calculate EAC. I wasn’t sure which type you were trying to list here. Can you please explain?

    EAC = AC + (BAC – EV) / CPI = BAC / CPI
    [use this formula if current project performance is typical; you expect the project to perform similarly till end of the project]

    Reply
    • Manickavel Arumugam says

      May 23, 2020 at 5:15 pm

      The formula is correct. It is the first scenario given in PMBOK Guide, Table 7-1. If the CPI is expected to be the same for the remainder of the project, then you can calculate EAC using this formula.

      EAC
      = Actual Cost + Remaining work / CPI
      = AC + (BAC-EV)/CPI
      = BAC/CPI

      Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

  • Email
  • Facebook
  • LinkedIn
  • Twitter
  • YouTube
PMP Exam Prep Live Online Training
10 Questions Quiz

You may also like

ITTOs Communications Management

How to remember ITTOs of Project Communications Management?

How to remember ITTOs of Project Communications Management? This is the seventh article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on […]

ITTOs Quality Management

How to remember ITTOs of Project Quality Management?

This is the fifth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project quality management. What is Project Quality Management? […]

PMP Practice Questions - Project Integration Management

PMP Practice Questions [Project Integration Management]

Below are few practice questions from the Project Integration Management knowledge area. All the questions are prepared with PMBOK Guide, Sixth Edition as the reference. Please give them a try. If you cannot answer to any of them, please refer to PMBOK Guide, Sixth Edition first and you will be able to find the correct […]

How to remember ITTOs of Project Resource Management?

How to remember ITTOs of Project Resource Management?

This is the sixth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project resource management. What is Project Resource Management? […]

ITTOs of Project Cost Management

How to remember ITTOs of Project Cost Management?

This is the fourth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project cost management. What is Project Cost Management? […]

Copyright © 2025 · pmDrill.com

PMI®, PMP®, and PMBOK® Guide are trademarks of Project Management Institute, Inc.