• Home
  • Beginners
  • Knowledge Areas
    • Integration
    • Scope
    • Schedule
    • Cost
    • Quality
    • Resource
    • Communications
    • Risk
    • Procurement
    • Stakeholder
  • Process Flow
  • Reference Materials
    • Books
    • Exam Prep Courses
    • Practice Questions
  • Tips
  • Lessons Learned
  • About

PM DRILL

PMP exam guide

You are here: Home / Knowledge Areas / Integration Management / Perform Integrated Change Control [Step-by-Step]

Perform Integrated Change Control [Step-by-Step]

November 11, 2018 By Manickavel Arumugam 4 Comments

8
SHARES
ShareTweet

A change request is a formal proposal to modify any document, deliverable or baseline.

Several project management processes may involve a change request.

Perform integrated change control is the process of reviewing all change requests and approving the changes. This process happens throughout the project for integrating change requests.

The approved change request may be a

  • Preventive action (an intentional activity that ensures the future performance of the project is aligned with the project management plan)
  • Corrective action (an intentional activity that realigns the future performance of the project with the project management plan)
  • Defect repair (an intentional activity that modifies a non-conforming product or product component) or
  • Updates (changes to formally controlled project documents)

The approved changes are implemented through the direct and manage project work process, to achieve the project’s objectives.

Perform Integrated Change Control

Table of Contents

  • Changes to the Project Management Plan
  • Perform Integrated Change Control [Step-by-Step]
  • Change Requests as Input
  • Change Requests as Output
  • Approved Change Requests as Input
  • Approved Change Requests as Output
  • Conclusion

Changes to the Project Management Plan

Project management plan should be baselined so that the actual project performance can be measured against the baseline. Before baselining the project management plan, it can be changed as many times as you want without going through any change control process. But, once the baseline is agreed, any further changes can happen only through formal change control process.

While developing the project management plan, we also should establish which project documents will be subject to the formal change control process.

Change management plan, a component of the project management plan, describes how the change requests will be formally authorized and incorporated.

Change log is a project document. The change log contains the status of all change requests.

In an Agile/ adaptive environment, the project manager’s focus is on ensuring the team has the ability to respond to changes.

Perform Integrated Change Control [Step-by-Step]

The first thing to do as a Project Manager is to minimize change requests in a project. You have to work to influence the causes of change requests.

You need to understand that, in spite of your efforts, changes are inevitable in a project.

Change Control Sequence

If you get a change request, the following are the suggested steps to address the change request:

  • Receive the change request. Any project stakeholder may request a change.
  • Identify/ clarify need for change.
  • Changes may be initiated verbally; in such cases, the changes should be documented into a proper change request in written form.
  • Record the change request in the change log.
  • Evaluate the impact of the requested change on various project objectives. The analysis should address various questions like:
    • Does the change affect the schedule?
    • Are we going to incur additional costs if the change is implemented?
    • Does it introduce any new risks?
    • How the overall project risk has changed? …
  • Once the evaluation is done, the Project Manager submits the following to the Change Control Board (CCB):
    • Change Request
    • Analysis Report
    • His/ her recommendation to the CCB
  • CCB reviews the change request, with the inputs given by Project Manager. After the review, CCB will take a decision either to accept the change request, defer it or reject it.

You should also note that depending on the level of authority given to the project manager, the change requests may be reviewed and approved by the project manager himself/ herself.

  • Customer or sponsor approval may be needed for certain change requests after CCB approval, in case they are not part of the CCB.
  • Update the change log with the decision of the CCB (approved, deferred or rejected)
  • Update the relevant components of the project management plan and the project documents.
  • Communicate the changes to relevant stakeholders
  • Implement the changes (approved change requests go back as an input to Direct and Manage Project Work process)
  • Check whether the changes are implemented (approved change requests are an input to Control Quality process)

Change Requests as Input

Do you know how many processes take change requests as an input?

It is only ONE process that takes change request as an input. Any guess which process it is?

Did you say Perform Integrated Change Control process? Yes, you are right.

Perform Integrated Change Control process is the only process where you will see change requests as an input. This makes sense as this is the only process where the change requests are reviewed and approved/ deferred/ rejected.

So, remember, if you see change requests as an input in any of the PMP exam question, the process should be Perform Integrated Change Control.

Change Requests as Output

Change requests can be generated throughout the project. PMBOK Guide has listed 25 processes where change requests may be generated. They are:

  • Initiating Process Group
    1. Identify Stakeholders
  • Planning Process Group
    1. Define Activities
    2. Develop Schedule
    3. Plan Risk Responses
    4. Plan Procurement Management
  • Executing Process Group
    1. Direct and Manage Project Work
    2. Manage Quality
    3. Acquire Resources
    4. Develop Team
    5. Manage Team
    6. Implement Risk Responses
    7. Conduct Procurements
    8. Manage Stakeholder Engagement
  • Monitoring and Controlling Process Group
    1. Monitor and Control Project Work
    2. Validate Scope
    3. Control Scope
    4. Control Schedule
    5. Control Costs
    6. Control Quality
    7. Control Resources
    8. Monitor Communications
    9. Monitor Risks
    10. Control Procurements
    11. Monitor Stakeholder Engagement

You do not need to remember all the 24 processes.

But, you should remember that all Monitoring and Controlling processes (except 4.6 Perform Integrated Change Control) will generate Change requests.

Approved Change Requests as Input

Don’t get confused between Change requests and Approved change requests. Approved change requests are inputs to three processes namely

  1. Direct and Manage Project Work
  2. Control Quality and
  3. Control Procurements

Approved Change Requests as Output

How many processes do you think can  approve change requests? Only ONE.

Which process is that? Yes, it is Perform Integrated Change Control.

As we have discussed throughout this article, the change requests are reviewed and approved in the Perform Integrated Change Control process. So, naturally, the output of this process should be Approved change requests.

Conclusion

Changes are an integral part of any project. It is the responsibility of the project manager to adequately manage the changes in a project.

Do you follow the above steps in your project?

Do you think the above flow chart helps you in your PMP exam preparation?

Leave your thoughts.

This article was triggered by an e-mail from Sarita, extract of which is shown below:

Your posts are very helpful.
Can you pls share the complete step by step process to follow in case of change management. As this is a very imp topic and many qs come in the exam.

If you have any similar requirements, you can drop me a mail at pmdrill.com@gmail.com. I will try my best to address them in my upcoming articles.

  • Author
  • Recent Posts
Manickavel Arumugam
Follow Me
Manickavel Arumugam
Certified Project Management Professional (PMP)®
Certified Risk Management Professional (PMI-RMP)®
An enthusiastic project management practitioner and trainer.
Manickavel Arumugam
Follow Me
Latest posts by Manickavel Arumugam (see all)
  • Yet another PMP Success Story - October 21, 2019
  • Project Management Using Microsoft Excel - September 10, 2019
  • PMI-RMP Course by uCertify – Is it for You? - August 3, 2019
8
SHARES
ShareTweet

Filed Under: Integration Management

Most Shared Posts

Comments

  1. pham tu says

    October 2, 2019 at 3:58 pm

    Dear sir
    Change request is not a output 4.6 (but input 4,6 => output approved CR).
    So i think M&C has out CR, except 4.6

    Reply
    • Manickavel Arumugam says

      October 3, 2019 at 6:36 am

      Absolutely Pham Tu. Thanks for highlighting that error. I have corrected it now.

      Reply
  2. Akhilesh Mishra says

    October 2, 2019 at 1:23 pm

    Sir, this article was very informative and useful. Kindly write a blog on 27 data analysis techniques as well if possible. Thanks for this blog !!!

    Reply
    • Manickavel Arumugam says

      October 3, 2019 at 6:20 am

      Thanks Akhilesh. Will add “27 data analysis techniques” to my to-do list.

      Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

  • Email
  • Facebook
  • LinkedIn
  • Twitter
  • YouTube
PMP Exam Prep Live Online Training
10 Questions Quiz

You may also like

project management plan for PMP exam

Project Management Plan [Study Notes for PMP Exam]

A project management plan is a formal, approved document that defines how the project is planned, executed, monitored, controlled and closed. In this article, we will understand why do we need a project management plan, what is the purpose of the project management plan and what are the various components of the project management plan. […]

9 Data Gathering Tools

9 Data Gathering Techniques You Should Know for PMP Exam

PMBOK® Guide has grouped most of the tools and techniques in a logical way, by their purpose. The following are the various groups used in PMBOK Guide , Sixth Edition: Data gathering techniques Data analysis techniques Data representation techniques Decision-making techniques Communication skills Interpersonal and team skills In addition, they also have several tools and […]

Resource leveling vs Resource smoothing

Resource Leveling and Resource Smoothing Explained with An Example

What is resource leveling? What is resource smoothing? Are they the same? If not, what is the difference? We will try to answer the above questions in this article. Resource Optimization Resource optimization is a tool/ technique used in the Develop Schedule process of Schedule Management knowledge area. Resource optimization is a schedule network analysis […]

How to remember ITTOs of Project Scope Management?

How to remember ITTOs of Project Scope Management?

This is the second article in the series “How to remember ITTOs”. I have written an earlier article on How to remember ITTOs of Integration management? ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project scope management. What is Project scope management? Project […]

Motivational Theories in PMP Exam

Motivational theories in PMP Exam

Recognition and Rewards is a tool/ technique used in the Develop Team process. Recognizing and rewarding desirable behavior is an important aspect of developing a team. Rewarding good work is a way of showing the people that the organization acknowledges and recognizes their effort. It is important to recognize the team throughout the project, without […]

Copyright © 2025 · pmDrill.com

PMI®, PMP®, and PMBOK® Guide are trademarks of Project Management Institute, Inc.