• Home
  • Beginners
  • Knowledge Areas
    • Integration
    • Scope
    • Schedule
    • Cost
    • Quality
    • Resource
    • Communications
    • Risk
    • Procurement
    • Stakeholder
  • Process Flow
  • Reference Materials
    • Books
    • Exam Prep Courses
    • Practice Questions
  • Tips
  • Lessons Learned
  • About

PM DRILL

PMP exam guide

You are here: Home / Knowledge Areas / Integration Management / Answers to PMP Practice Questions [Project Integration Management]

Answers to PMP Practice Questions [Project Integration Management]

July 12, 2018 By Manickavel Arumugam 7 Comments

ShareTweet

Here are the answers to the PMP® Practice Questions on Project Integration Management, which I have posted earlier. I have explained why the choice is correct. I have also given references to PMBOK® Guide, Sixth Edition, wherever it is relevant.

If you are yet to see the practice questions, please check out the questions here: PMP® Practice Questions [Project Integration Management].

Answers to PMP Practice Questions (Project Integration Management)

Answers to PMP Practice Questions (Project Integration Management)

1. Correct answer: Choice D.

Change Requests can be an input to only one process, which is Perform Integrated Change Control. Change Request, wherever generated in the project, has to be an input to this process. Please remember that only Perform Integrated Change Control process can review and approve/ reject the change requests.

2. Correct answer: Choice C.

Project Charter is the document that authorizes the existence of a project and empowers the project manager to obtain resources for the project. So, the project manager should show the project charter, which should convince the functional manager.

3. Correct answer: Choice C.

Describing the product, service or result boundaries, and acceptance criteria is the benefit of Define Scope Process. The remaining are all the benefits of Develop Project Charter process.
Ref: PMBOK Guide, Sixth Edition, Page 75 & 150

4. Correct answer: Choice B.

Projects are initiated by an entity external to the project such as a sponsor, program or project management office (PMO), or a portfolio governing body chairperson or authorized representative.
Ref: PMBOK Guide, Sixth Edition, Page 77

5. Correct answer: Choice B.

The business case describes the necessary information from a business standpoint to determine whether the expected outcomes of the project justify the required investment.
Ref: PMBOK Guide, Sixth Edition, Page 77

6. Correct answer: Choice A.

Acceptance criteria is included as part of Project Scope Statement, while the other three are typically seen in Project Charter.
Ref: PMBOK Guide, Sixth Edition, Page 155

7. Correct answer: Choice D.

Formal authorization of a project happens at the time of project charter, not at the kick-off meeting.
Ref: PMBOK Guide, Sixth Edition, Page 86

8. Correct answer: Choice C.

While you might be carrying out all the other choices with regards to change requests, the most important role of project manager is to work towards preventing unnecessary changes in the project.

9. Correct answer: Choice B.

From the question, you can understand that the Project Charter has already been developed. Next step is to develop the project management plan.

10. Correct answer: Choice D.

As per the PMI Code of Ethics and Professional Conduct, you should bring violations of the code to the attention of senior management at the company and possibly PMI. However, you should get the facts together and gather evidence before taking either of those steps.

Conclusion

If you don’t agree with any of the answers above, feel free to post your views here. Let us discuss and come to a conclusion. If you need any clarification or further explanation on any of the concepts discussed above, please leave your comments below. I will try to address them.

  • Author
  • Recent Posts
Manickavel Arumugam
Follow Me
Manickavel Arumugam
Certified Project Management Professional (PMP)®
Certified Risk Management Professional (PMI-RMP)®
An enthusiastic project management practitioner and trainer.
Manickavel Arumugam
Follow Me
Latest posts by Manickavel Arumugam (see all)
  • Yet another PMP Success Story - October 21, 2019
  • Project Management Using Microsoft Excel - September 10, 2019
  • PMI-RMP Course by uCertify – Is it for You? - August 3, 2019
ShareTweet

Filed Under: Integration Management

Most Shared Posts

Comments

  1. TG Prakash says

    September 15, 2020 at 5:38 pm

    Questions 2,3 & 6 were wrong could able to gone through your explanation and understand the essence.

    Thanks
    Prakash

    Reply
  2. Vaibhav Bhasin says

    July 12, 2020 at 6:09 pm

    Answer of 2nd question should be A –> As it is mentioned in Question, you have to negotiate with functional manager. So i think A represents the best Answer, If I will have to show the project charter, than what’s the point of negotiation. Its just like giving order. This is my perception. Please correct me sir.

    Thanks

    Reply
    • Manickavel Arumugam says

      July 27, 2020 at 11:20 am

      Having a project charter does not mean that we can order functional managers? We still have to negotiate with the FMs to get the right resources at the right time in the right quantities.

      Reply
  3. Vishwa says

    June 23, 2020 at 3:50 pm

    I’m Vishwa, your current batch student sir. I got 8 answers correct.
    Ques 2 nad 6 went wrong. I went through the explanation and understood. Thanks for sharing sir

    Reply
    • Manickavel Arumugam says

      June 29, 2020 at 12:58 pm

      Wonderful Vishwa! That’s an excellent score.

      Reply
  4. Deepak Chaudhary says

    April 6, 2020 at 9:25 pm

    Hi, Thanks for sharing free questions and answers on Project Integration management. It’s highly beneficial for all who are preparing for PMP examination.Thanks again

    Reply
    • Manickavel Arumugam says

      April 10, 2020 at 6:00 am

      You are welcome

      Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

  • Email
  • Facebook
  • LinkedIn
  • Twitter
  • YouTube
PMP Exam Prep Live Online Training
10 Questions Quiz

You may also like

How to remember ITTOs of Project Risk Management?

How to remember ITTOs of Project Risk Management?

This is the eighth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project risk management. What is Project Risk Management? […]

9 Data Gathering Tools

9 Data Gathering Techniques You Should Know for PMP Exam

PMBOK® Guide has grouped most of the tools and techniques in a logical way, by their purpose. The following are the various groups used in PMBOK Guide , Sixth Edition: Data gathering techniques Data analysis techniques Data representation techniques Decision-making techniques Communication skills Interpersonal and team skills In addition, they also have several tools and […]

Closing process group

Sequence of Activities in Closing Process

Closing process group includes only one process, namely, Close project or phase. This process belongs to the Integration knowledge area. Close project or phase is the process during which we formally close the project or phase. Generally, the project charter will include project success criteria, project exit criteria and who will sign off the project. […]

Resource leveling vs Resource smoothing

Resource Leveling and Resource Smoothing Explained with An Example

What is resource leveling? What is resource smoothing? Are they the same? If not, what is the difference? We will try to answer the above questions in this article. Resource Optimization Resource optimization is a tool/ technique used in the Develop Schedule process of Schedule Management knowledge area. Resource optimization is a schedule network analysis […]

project management plan for PMP exam

Project Management Plan [Study Notes for PMP Exam]

A project management plan is a formal, approved document that defines how the project is planned, executed, monitored, controlled and closed. In this article, we will understand why do we need a project management plan, what is the purpose of the project management plan and what are the various components of the project management plan. […]

Copyright © 2025 · pmDrill.com

PMI®, PMP®, and PMBOK® Guide are trademarks of Project Management Institute, Inc.