You are here: Home / Process Flow / How to remember ITTOs of Project Scope Management?

How to remember ITTOs of Project Scope Management?

April 7, 2018 By Manickavel Arumugam 8 Comments

4
SHARES
ShareTweet

This is the second article in the series “How to remember ITTOs”.

I have written an earlier article on How to remember ITTOs of Integration management? ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs.

In this article, we will focus on Project scope management.

How to remember ITTOs of Project Scope Management?

What is Project scope management?

Project scope management is the knowledge area in which the team performs the following major activities:

  • Collects requirements
  • Defines the scope from requirements by developing the project scope statement
  • Decomposing the scope further down into more manageable components by developing the Work Breakdown Structure (WBS)
  • Inspecting the verified deliverables along with customer to validate the scope
  • Monitoring the scope performance of the project and controlling any changes to scope

Process Flow in Project Scope Management

I have suggested process flow diagrams as a way to remember and map the concepts in mind. Following the same approach, I have given the process flow diagram for Project Scope Management below.

Scope management process flow

I have included ONLY the major inputs and outputs, so that it is easier to understand rather than complicating it too much. Please note that it does NOT include ALL inputs and outputs. I have included only those inputs and outputs, which I felt are important. Please refer to PMBOK Guide for a complete list of ITTOs.

The best way to get the ITTOs in your mind is to draw the process flow diagram yourself. It would help your mind to map the inputs and outputs to the processes; and you would not forget it.

Tips to remember ITTOs of Project Scope Management

  1. Organizational Process Assets is an input to 47 processes; only two processes do not take OPA as an input. They are 5.5 Validate Scope and 11.7 Monitor Risks.
  2. Expert Judgment is a Tool & Technique used in all the 4 planning processes of Project Scope Management.
  3. Enterprise Environmental Factors is an input to all the 4 planning processes of Project Scope Management.
  4. Once scope management plan is developed in 5.1 Plan Scope Management, it becomes an input to all the following 5 processes in Project Scope Management.
  5. Requirements documentation is developed in 5.2 Collect requirements. It becomes an input to all the following 4 processes in Project Scope Management.
  6. Work performance data is an input to the 2 controlling processes; and work performance information is the relevant output from those controlling processes.
  7. For all Monitoring & Controlling processes, change requests is an output; the only exception is Perform Integrated Change Control. In this process, change requests is an input and Approved change requests is an output.
  8. Decomposition is a tool used in 5.4 Create WBS; it is also used in 6.2 Define Activities. In 5.4, the project scope statement is decomposed into work packages; while in 6.2, the work packages are further decomposed into activities.
  9. Inspection is a tool used in 5.5 Validate Scope; it is also used in 8.3 Control Quality and 12.3 Control Procurements. In 8.3, the deliverables are inspected by internal quality control team; following this in 5.5, the deliverables are inspected by the Customer. It is general practice to perform internal quality control ahead of scope validation by customer; but, under special circumstances, you could perform both activities simultaneously. In 12.3, inspection is carried out on the deliverables from seller.

Conclusion

What is your approach to remember ITTOs in Project Scope Management? Do you think the above approach is good? Do you have any other tips you want me to include in the above list?

Share your opinions and comments in the comments box below. I will continue to work on the process flow diagram for the other knowledge areas.

  • Author
  • Recent Posts
Manickavel Arumugam
Follow Me
Manickavel Arumugam
Certified Project Management Professional (PMP)®
Certified Risk Management Professional (PMI-RMP)®
An enthusiastic project management practitioner and trainer.
Manickavel Arumugam
Follow Me
Latest posts by Manickavel Arumugam (see all)
  • Yet another PMP Success Story - October 21, 2019
  • Project Management Using Microsoft Excel - September 10, 2019
  • PMI-RMP Course by uCertify – Is it for You? - August 3, 2019
4
SHARES
ShareTweet

Filed Under: Process Flow, Scope Management

Most Shared Posts

Comments

  1. Ahmed Younis says

    July 2, 2020 at 9:11 pm

    Excuse me Mr. Manickavel Arumugam,

    Is Quality reports can be considered as a major input in the validated scope process also ?

    Thanks for you great help.

    Regards

    Reply
    • Manickavel Arumugam says

      July 8, 2020 at 6:57 pm

      Yes, you consider it as a major input. PMI considers this as an input to the process and believes that the quality reports might be reviewed before accepting the deliverables.

      Reply
  2. Ahmed Younis says

    July 2, 2020 at 8:53 pm

    Great work Mr. Manickavel Arumugam. Great thanks for your efforts.

    Regards

    Reply
    • Manickavel Arumugam says

      July 8, 2020 at 6:45 pm

      Thanks Ahmed.

      Reply
  3. Jyothi says

    April 4, 2019 at 2:54 am

    Dear Sir, Thank you,
    Appreciate your great work, But could you explain what the dark circles in the figure above and all other figures likewise mean:

    Reply
    • Manickavel Arumugam says

      April 4, 2019 at 7:58 am

      Thanks Jyothi. I believe you are referring to the circles with numbers inside the circle.

      Circle with (1) refers to scope management plan, Circle with (2) refers to Requirements management plan. I have used these circles as connectors.

      For example, look at the process 5.4 Create WBS. You can see from the above flow chart that 1 & 3 are inputs. It means scope management plan (1) and requirements documentation (3) are inputs to this process.

      Similarly, if you look at the M&C processes, they have 1, 2, 3 & 4 are inputs. It means the inputs to the process are scope management plan, requirements management plan, requirements documentation & requirements traceability matrix.

      If you still have any doubts, please let me know.

      Reply
  4. Atif says

    May 2, 2018 at 5:22 am

    Appreciate your work.

    waiting your posts for other Knowledge Areas

    THANKS

    Reply
    • Manickavel Arumugam says

      May 2, 2018 at 7:34 pm

      Thanks Atif. I believe you have seen the process flow diagram for five knowledge areas, which I have posted already.

      Working on the remaining five knowledge areas. Will post them soon.

      Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

  • Email
  • Facebook
  • LinkedIn
  • Twitter
  • YouTube
PMP Exam Prep Live Online Training
10 Questions Quiz

You may also like

Resource leveling vs Resource smoothing

Resource Leveling and Resource Smoothing Explained with An Example

What is resource leveling? What is resource smoothing? Are they the same? If not, what is the difference? We will try to answer the above questions in this article. Resource Optimization Resource optimization is a tool/ technique used in the Develop Schedule process of Schedule Management knowledge area. Resource optimization is a schedule network analysis […]

ITTOs Communications Management

How to remember ITTOs of Project Communications Management?

How to remember ITTOs of Project Communications Management? This is the seventh article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on […]

Answers to PMP Practice Questions (Project Integration Management)

Answers to PMP Practice Questions [Project Integration Management]

Here are the answers to the PMP® Practice Questions on Project Integration Management, which I have posted earlier. I have explained why the choice is correct. I have also given references to PMBOK® Guide, Sixth Edition, wherever it is relevant. If you are yet to see the practice questions, please check out the questions here: […]

project management plan for PMP exam

Project Management Plan [Study Notes for PMP Exam]

A project management plan is a formal, approved document that defines how the project is planned, executed, monitored, controlled and closed. In this article, we will understand why do we need a project management plan, what is the purpose of the project management plan and what are the various components of the project management plan. […]

How to remember ITTOs of Project Resource Management?

How to remember ITTOs of Project Resource Management?

This is the sixth article in the series “How to remember ITTOs”. You can find all the articles in this series here: How to remember ITTOs series. ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs. In this article, we will focus on Project resource management. What is Project Resource Management? […]